Rapid Pre-construction Forecasting of Schedule Overruns: A Machine Learning Regression Approach

The Open Construction & Building Technology Journal • 05 Nov 2026 • RESEARCH ARTICLE • DOI: 10.2174/0118748368518070261027111727

Abstract

Introduction/Objective

This study developed and validated a parsimonious machine-learning regression model that estimates schedule overruns for building construction projects prior to project start.

Methods

Using a dataset of 60 completed building projects in Lebanon, each with 11 pre-project predictors, an XGBoost regression model was trained and tested on an independent dataset, with repeated cross-validation and hyperparameter tuning.

Results

Averaged over repeated randomized train/test partitions, the trained and tuned model achieved an R2 = 79.6% (adjusted R2 = 74.3%), a mean absolute error of 4.36 ± 0.48 percentage points (95% CI: 3.42–5.30), and a median coverage near the nominal 90% for empirical prediction intervals.

Discussion

The regression-based approach extends existing delay-risk assessment by estimating delay magnitude rather than only the risk class, while factor-importance analysis identified owner/client performance, legal/permit issues, design quality, and project manager experience as the major drivers of delay.

Conclusion

The model provides a practical decision-support tool for project managers to estimate the expected magnitude of delay and its uncertainty before construction initiation, requiring only eleven readily obtainable pre-project inputs.

Keywords: Building construction, Project scheduling, Construction delays, Machine learning, XGBoost.